Brandenburg allows buildings without habitable rooms up to 75 m³ gross volume without a permit application under § 61 BbgBO. That makes every Konvel model from Solo to Galerie permit-free.
- Permit-free up to
- 75 m³
- Measured by
- Brutto-Rauminhalt
- Legal basis
- § 61 BbgBO
Which Konvel models are permit-free in Brandenburg?
| Model | Floor area | Gross volume | Status |
|---|---|---|---|
| Konvel Solo | ~12 m² | ~30 m³ | Permit-free |
| Konvel Studio | ~15 m² | ~38 m³ | Permit-free |
| Konvel Werkstatt | ~18 m² | ~43 m³ | Permit-free |
| Konvel Galerie | ~21 m² | ~51 m³ | Permit-free |
Floor area from the external wall dimensions, volume with the highest roof edge — deliberately rounded up so the estimate stays on the safe side.
What to watch in Brandenburg
Around Berlin many plots fall under development plans or design statutes that can restrict outbuildings in size, height or roof shape. Check your municipality's plan before fixing the spot in the garden — the state rule is only the upper limit.
What applies even without a permit
Even where no permit is required by the state, these constraints still apply:
- No Aufenthaltsraum (formally — see below)
- No toilet, no bathroom, no kitchen
- No fireplace: no wood stove, no chimney, no permanent stove
- No fixed connection to water mains or sewerage
- Average wall height max. 3.0 m (Schleswig-Holstein: 2.75 m)
- 3 m boundary setback for buildings over ~30 m³
- Boundary placement only for very small buildings, max. 9 m along one boundary, max. 15 m total
- A permanent concrete foundation may trigger a permit requirement — the structure must remain "removable in principle"
- Rainwater must drain on the customer's own plot
The Aufenthaltsraum trap — relevant in every Bundesland
Strictly speaking, every state's building code says the permit-free structure cannot be an Aufenthaltsraum — a room intended for more than transient human occupation. An office where someone works eight hours a day is, formally, an Aufenthaltsraum.
Exception 1: Außenbereich (outside built-up areas)
If the plot lies outside contiguously developed parts of town (Außenbereich per § 35 BauGB), the rules are significantly stricter. A permit is often required regardless of size. Konvel buyers are mostly in the Innenbereich; for rural postcodes we review the case with you in advance.
Exception 2: Allotment gardens (Kleingartenanlagen)
Allotment gardens are governed by the federal Bundeskleingartengesetz, not state law. Maximum 24 m² including covered terrace, no permanent residence, no modern office use. Konvel therefore does not sell to allotment-garden customers — buildings there are legally limited to traditional Gartenlauben.
Bebauungsplan can override everything
Local development plans (Bebauungsplan) can be stricter than the state building code. Even where a structure would be permit-free under the LBauO, a Bebauungsplan can ban outbuildings entirely, limit heights, prescribe roof forms, specify cladding materials or require larger setbacks. The definitive answer comes only from the local Bauamt.
Common questions about Brandenburg
- Do I need a building permit for a garden office in Brandenburg?
- Generally not: under § 61 BbgBO, buildings without habitable rooms up to 75 m³ are permit-free, and Konvel Solo, Konvel Studio, Konvel Werkstatt and Konvel Galerie stay below that. Development plan, setback and the habitable-room question still apply.
- How is the threshold measured in Brandenburg?
- By gross volume: external wall dimensions times building height. We calculate with the highest roof edge and round up so no model is misjudged by a narrow margin. The building authority states the binding method.
- What do I have to observe in Brandenburg even without a permit?
- The setback of generally 3 m to the neighbour, the local development plan, and the rule that permit-free buildings are formally not habitable rooms. Stricter rules apply in the Außenbereich and in allotment gardens.