Building permit for a garden office in Nordrhein-Westfalen

North Rhine-Westphalia applies a double threshold under § 62 BauO NRW: buildings without habitable rooms are permit-free up to 75 m³ gross volume, and the floor area must not exceed 30 m². All four Konvel models meet both values.

Permit-free up to
75 m³ oder 30 m²
Measured by
BRI + Grundfläche
Legal basis
§ 62 BauO NRW

Which Konvel models are permit-free in Nordrhein-Westfalen?

ModelFloor areaGross volumeStatus
Konvel Solo~12~30Permit-free
Konvel Studio~15~38Permit-free
Konvel Werkstatt~18~43Permit-free
Konvel Galerie~21~51Permit-free

Floor area from the external wall dimensions, volume with the highest roof edge — deliberately rounded up so the estimate stays on the safe side.

What to watch in Nordrhein-Westfalen

NRW is our home market: Konvel advises from Gelsenkirchen and the first Konvel stands in the Ruhr area. The building code was modernised in 2018; since then garden offices of this size have been straightforward — as long as the 3 m setback, the development plan and the habitable-room question are respected.

What applies even without a permit

Even where no permit is required by the state, these constraints still apply:

  • No Aufenthaltsraum (formally — see below)
  • No toilet, no bathroom, no kitchen
  • No fireplace: no wood stove, no chimney, no permanent stove
  • No fixed connection to water mains or sewerage
  • Average wall height max. 3.0 m (Schleswig-Holstein: 2.75 m)
  • 3 m boundary setback for buildings over ~30 m³
  • Boundary placement only for very small buildings, max. 9 m along one boundary, max. 15 m total
  • A permanent concrete foundation may trigger a permit requirement — the structure must remain "removable in principle"
  • Rainwater must drain on the customer's own plot

The Aufenthaltsraum trap — relevant in every Bundesland

Strictly speaking, every state's building code says the permit-free structure cannot be an Aufenthaltsraum — a room intended for more than transient human occupation. An office where someone works eight hours a day is, formally, an Aufenthaltsraum.

Exception 1: Außenbereich (outside built-up areas)

If the plot lies outside contiguously developed parts of town (Außenbereich per § 35 BauGB), the rules are significantly stricter. A permit is often required regardless of size. Konvel buyers are mostly in the Innenbereich; for rural postcodes we review the case with you in advance.

Exception 2: Allotment gardens (Kleingartenanlagen)

Allotment gardens are governed by the federal Bundeskleingartengesetz, not state law. Maximum 24 m² including covered terrace, no permanent residence, no modern office use. Konvel therefore does not sell to allotment-garden customers — buildings there are legally limited to traditional Gartenlauben.

Bebauungsplan can override everything

Local development plans (Bebauungsplan) can be stricter than the state building code. Even where a structure would be permit-free under the LBauO, a Bebauungsplan can ban outbuildings entirely, limit heights, prescribe roof forms, specify cladding materials or require larger setbacks. The definitive answer comes only from the local Bauamt.

Common questions about Nordrhein-Westfalen

Do I need a building permit for a garden office in Nordrhein-Westfalen?
Generally not: under § 62 BauO NRW, buildings without habitable rooms up to 75 m³ oder 30 m² are permit-free, and Konvel Solo, Konvel Studio, Konvel Werkstatt and Konvel Galerie stay below that. Development plan, setback and the habitable-room question still apply.
How is the threshold measured in Nordrhein-Westfalen?
By gross volume: external wall dimensions times building height. We calculate with the highest roof edge and round up so no model is misjudged by a narrow margin. The building authority states the binding method.
What do I have to observe in Nordrhein-Westfalen even without a permit?
The setback of generally 3 m to the neighbour, the local development plan, and the rule that permit-free buildings are formally not habitable rooms. Stricter rules apply in the Außenbereich and in allotment gardens.

We check your site in Nordrhein-Westfalen in advance.

Enter your postcode in the configurator — we come back with a first assessment and a non-binding offer.